Newsticker

Teaser_SocialMedia_Autostore_600x338.jpg
Dec 6, 2017

Ultra-modern logistics center on the verge of operationability

To meet the ever-growing customer demands for fast supply and adherence to delivery dates,  the Baumer focus is on centralized and automated logistics. The ultra-modern logistics center which is part of...

Teaser_Unternehmen_Newsticker_Fahne_600x338.jpg
Oct 25, 2017

Move into the new building

Mid October, the first 50 employees moved from provisionally rented offices into the modern premises of the new Baumer High-Tech Center at Lake Constance. In a symbolic act, the Baumer colors were hoisted...

Luftaufnahme_20170412_0002_600x338.jpg
Apr 14, 2017

The façade now presents its final look

Matching the begin of springtime, the new office building has been released from the scaffolding and presents itself with a real wow-effect. The quick progress is now obvious – with the sun protection having been installed and...

Teaser_DSC_9381_Richtfest_600x338.jpg
Feb 9, 2017

Baumer celebrated the topping out ceremony

On 9 February 2017 we celebrated an important milestone in the construction phase of the new Baumer site in the town of Stockach. Craftsmen, Baumer employees, representatives of the Townhall and Municipality as well our new neighbors...

Luftaufnahme_20161124_0007_600x338.jpg
Nov 28, 2016

The shell of the office building being the first construction section has been finalised

Barely two months after completion of the primary foundation plates, half of the new office building is ready and the workers are busy with preparing the roof. Even the building hosting logistics now presents its roof...

Luftaufnahme_20160921_0006_600x338.jpg
Sep 26, 2016

The buildings get taller each day – creating a forest of pillars

This week, first concrete pillars for the future production building were erected and anchored in the soil. The precast concrete elements with up to 18m in height pave the way for the next step in the construction work...

Luftaufnahme_20160907_0005_600x338.jpg
Sep 9, 2016

Construction works are going full speed ahead

Structural work of the technical center will be completed soon, preparations for fitting the ceiling panel are in full swing...

Teaser_Unternehmen_Newsticker_Rohbauarbeiten_600x338.jpg
Jun 23, 2016

Beginning of the structural work

Around 25,000 m3 of earth have been moved in the last two months. Having disposed of about 2/3, the remainder is going to be used for the site’s landscaping and redesign..

160621_Baumer_Spatenstich_600x338.jpg
Apr 13, 2016

Ground-breaking ceremony in April - earthwork is in full swing

After a year of intensive planning, Baumer was able to celebrate an important milestone in April: the construction work for the state-of-the-art high-tech center started...

Teaserbilder_Unternehmen_Zukunft_600x338.jpg
Nov 2, 2015

The future has already begun

Reputed as an attractive employer in the high-tech sector, Baumer has already gained a foothold in the Stockach region...