Sep 9, 2016

Construction works are going full speed ahead

Structural work of the technical center will be completed soon, preparations for fitting the ceiling panel are in full swing. First walls of the production building are already in place.

Two workforces in parallel work on the buildings to host production/logistics and administration. While first walls of the production building have already been erected and everything is being prepared for the concrete pillars scheduled for the week to come,  some workers are all busy with laying strip and base foundations for the future office building.

Luftaufnahme_20160907_0005_600x338.jpg
Luftaufnahme_20160907_0021_600x338.jpg
To the top